Posted on September 23, 2019
Author Jacque Ryan, WKVI
The water project in North Judson is wrapping up just as the wastewater project is getting started.
As previously reported, this project will involve the installation of a new sewer dedicated to storm water, rehabilitation of the existing wastewater collection system and upgrades to the wastewater treatment plant will also be made.
CommonWealth Engineering Intern Sarah Prizio came before Town Council members last Monday to give them an update about where the project stands.
She noted that Division A, the sewer separation, still hasn’t mobilized but some behind the scenes prep work is being done to prepare for that.
However, Division B has mobilized and crews will start working on the site in the coming weeks. She presented them with a pay application related to mobilization and the associated bonds for that portion of the project. She noted that it totaled $53,690.20 with retainage amount of $2,825.80.
That pay application received unanimous approval from the council.