Tuesday, March 19, 2019

NJ Town Council Updated on Water and Wastewater Projects

Posted on March 19, 2019
Author Jacque Ryan, WKVI

North Judson Town Council members were given an update about their water and wastewater projects when they met Monday night.

CommonWealth Project Engineer Rob Bellucci provided members with a print-out of draft minutes from the first water project construction meeting that was held last week. He noted that it provides a snapshot of what’s been done up to this point.

He also gave members updated schedules and noted that they will begin to see some mobilization on the water project soon.

The contractor who is responsible for the well and some of the miscellaneous pipe work in and around the water plant will be moving trailers in by the end of the week.

Bellucci added the well driller and the water tower contractor are planning to mobilize within the first week of April.

Meanwhile, on the Wastewater project, Bellucci said that all necessary documentation has been submitted to the USDA. He explained that approval was received from the state and now they’re just waiting to get the green light from the federal level in order to move forward with taking that project to bid.

Bellucci reminded officials to contact him if any public concerns arise so project officials can address the issue as soon as possible.

No comments: